FAT Readiness Evaluation
Northwind Robotics — Line 4 Retrofit
Palletising cell retrofit. Customer FAT scheduled at our Aarhus facility.
Comparison
- T-1 week8 Jun 2026
- T-4 weeks18 May 2026
- T-8 weeks20 Apr 2026
Hover or tab to a dimension to read its statement at each round.
What the next rung asks for
Weakest dimensions · T-1 week
- Open Defects34
No open defect would block a FAT test step; the remainder carry agreed dates.
- Design Documentation45
The document pack has been issued to the customer ahead of the FAT and acknowledged as received.
- Hardware Build45
The machine has run at rated speed and duty using production-representative material.
Scores
Movement is measured from T-8 weeks to T-1 week.
| Dimension | T-1 week | T-4 weeks | T-8 weeks | Move |
|---|---|---|---|---|
| Test Specification & Acceptance Criteria | 5/5 | 4/5 | 2/5 | +3 |
| Design Documentation | 4/5 | 3/5 | 1/5 | +3 |
| Hardware Build | 4/5 | 3/5 | 1/5 | +3 |
| Software & Controls | 5/5 | 3/5 | 2/5 | +3 |
| Integration Dry Run | 5/5 | 3/5 | 1/5 | +4 |
| Safety & Compliance | 4/5 | 3/5 | 2/5 | +2 |
| Open Defects | 3/5 | 3/5 | 2/5 | +1 |
| Stakeholder & Logistics Readiness | 4/5 | 3/5 | 2/5 | +2 |