FAT Readiness Evaluation

Northwind Robotics — Line 4 Retrofit

Palletising cell retrofit. Customer FAT scheduled at our Aarhus facility.

Comparison

  • T-1 week8 Jun 2026
  • T-4 weeks18 May 2026
  • T-8 weeks20 Apr 2026
Radar of 8 dimensions scored 1 to 5, comparing T-1 week, T-4 weeks, T-8 weeks. The table below carries the same values.Test SpecDocumentationHardwareSoftwareDry RunSafetyDefectsStakeholders12345

Hover or tab to a dimension to read its statement at each round.

What the next rung asks for

Weakest dimensions · T-1 week

  • Open Defects34

    No open defect would block a FAT test step; the remainder carry agreed dates.

  • Design Documentation45

    The document pack has been issued to the customer ahead of the FAT and acknowledged as received.

  • Hardware Build45

    The machine has run at rated speed and duty using production-representative material.

Scores

Movement is measured from T-8 weeks to T-1 week.

DimensionT-1 weekT-4 weeksT-8 weeksMove
Test Specification & Acceptance Criteria5/54/52/5+3
Design Documentation4/53/51/5+3
Hardware Build4/53/51/5+3
Software & Controls5/53/52/5+3
Integration Dry Run5/53/51/5+4
Safety & Compliance4/53/52/5+2
Open Defects3/53/52/5+1
Stakeholder & Logistics Readiness4/53/52/5+2