FAT Readiness Evaluation
Halden Marine — Deck Crane Skid
Hydraulic deck crane power skid for a newbuild platform supply vessel. FAT witnessed by class.
Comparison
- T-1 week5 Aug 2026
- T-4 weeks17 Jul 2026
- T-16 weeks24 Apr 2026
Hover or tab to a dimension to read its statement at each round.
What the next rung asks for
Weakest dimensions · T-1 week
- Open Defects34
No open defect would block a FAT test step; the remainder carry agreed dates.
- Design Documentation45
The document pack has been issued to the customer ahead of the FAT and acknowledged as received.
- Hardware Build45
The machine has run at rated speed and duty using production-representative material.
Rounds
T-1 week
5 Aug 2026 · 8/8 scored
4.1T-4 weeks
17 Jul 2026 · 8/8 scored
3.8T-8 weeks
19 Jun 2026 · 8/8 scored
2.9T-12 weeks
22 May 2026 · 8/8 scored
2.0T-16 weeks
24 Apr 2026 · 8/8 scored
1.3
Every round is kept. The radar draws 3 at a time — pin the ones you want to compare and a fourth pin releases the oldest.
Scores
Movement is measured from T-16 weeks to T-1 week.
| Dimension | T-1 week | T-4 weeks | T-16 weeks | Move |
|---|---|---|---|---|
| Test Specification & Acceptance Criteria | 5/5 | 4/5 | 2/5 | +3 |
| Design Documentation | 4/5 | 3/5 | 1/5 | +3 |
| Hardware Build | 4/5 | 4/5 | 1/5 | +3 |
| Software & Controls | 4/5 | 4/5 | 1/5 | +3 |
| Integration Dry Run | 4/5 | 3/5 | 1/5 | +3 |
| Safety & Compliance | 4/5 | 4/5 | 2/5 | +2 |
| Open Defects | 3/5 | 4/5 | 1/5 | +2 |
| Stakeholder & Logistics Readiness | 5/5 | 4/5 | 1/5 | +4 |