Maturity

FAT Readiness Evaluation

Halden Marine — Deck Crane Skid

Hydraulic deck crane power skid for a newbuild platform supply vessel. FAT witnessed by class.

Comparison

  • T-1 week5 Aug 2026
  • T-4 weeks17 Jul 2026
  • T-16 weeks24 Apr 2026
Radar of 8 dimensions scored 1 to 5, comparing T-1 week, T-4 weeks, T-16 weeks. The table below carries the same values.Test SpecDocumentationHardwareSoftwareDry RunSafetyDefectsStakeholders12345

Hover or tab to a dimension to read its statement at each round.

What the next rung asks for

Weakest dimensions · T-1 week

  • Open Defects34

    No open defect would block a FAT test step; the remainder carry agreed dates.

  • Design Documentation45

    The document pack has been issued to the customer ahead of the FAT and acknowledged as received.

  • Hardware Build45

    The machine has run at rated speed and duty using production-representative material.

Rounds

Every round is kept. The radar draws 3 at a time — pin the ones you want to compare and a fourth pin releases the oldest.

Scores

Movement is measured from T-16 weeks to T-1 week.

DimensionT-1 weekT-4 weeksT-16 weeksMove
Test Specification & Acceptance Criteria5/54/52/5+3
Design Documentation4/53/51/5+3
Hardware Build4/54/51/5+3
Software & Controls4/54/51/5+3
Integration Dry Run4/53/51/5+3
Safety & Compliance4/54/52/5+2
Open Defects3/54/51/5+2
Stakeholder & Logistics Readiness5/54/51/5+4